The Gantt chart below shows the intended project schedule. As the project progresses, the schedule may be subjected to change. Please consult the Project Progress page for continuous updates on our work as it is completed.
Key tasks and their time scales are discussed below the Gantt chart. More detail on the key stages in the project can be found in the method statement.
Please click on the chart to view an enlarged version.
Key tasks and their time scales are discussed below the Gantt chart. More detail on the key stages in the project can be found in the method statement.
Please click on the chart to view an enlarged version.
Building and testing of wallettes
Wallettes will be constructed using the model material and tested under four-line loads in order to obtain the material’s stress-strain relationship and flexural strength. Three wallettes will be tested for both orthogonal orientations of the material, i.e. six tests in total. It is assumed that construction of the wallettes will take 9 days, and 3 days are allowed for testing.
Construction of model
Following construction and testing of the wallettes, we intend to begin work on the model vault. Prior to this task, we will allow time for a 'dry' (without mortar) assembly of the model in order to determine the stability of the model during construction. This 'dry' assembly is not shown on the schedule. There have been 19 days allocated to the task of constructing the model. This is one of the most fundamental tasks in our schedule; more time can be allowed prior to examinations if deemed necessary.
Interim report preparation and write-up
The interim report is due on Friday 31st January and work on the report will begin on Monday 25th November. This should allow ample time before and after the Christmas exam period, whilst allowing focus to be directed towards the design project during the first two weeks of Semester 2. The interim report will present a summary of work completed to date, a comprehensive and critical review of all relevant literature studied, and a review of the planning document (including the project schedule shown above).
Lab tests (elastic)
The model will be subjected to evenly distributed lead weights to simulate self weight in the real structure, and the deformation will be monitored for varying heights of spandrel fill. A larger time window has been allocated to the elastic testing phase than the failure tests because it is essential that the model has time to return to its initial state after unloading. Failure to allow the model to recover between tests would lead to unreliable results.
Lab tests (failure)
A one week gap has been left after the elastic testing is completed before commencing the second testing phase. During the 'failure' test the model will be driven beyond the limits of serviceability by spreading the supports and driving the structure to collapse. Repairs will be carried out using FRP and their affect will be assessed. It is deemed that 12 days will be ample time to prepare and conduct this phase of testing.
Thesis write-up
It is intended that we will begin to write up our thesis during the week commencing Monday 3rd February. The thesis write up will take place in conjunction with the recording and analysis of results. Nine weeks in total have been allowed for the write-up; however it is intended that it will be written in seven weeks to allow a two week time window for proof reading, printing and binding.
Oral Presentation
Although this task will only take one day, four weeks have been allowed on the project schedule as the date shall not be confirmed until nearer the presentation. This will be an informal opportunity for the author to present the thesis to the second reader and project supervisor and for them to assess the author's depth of understanding of the project.
Wallettes will be constructed using the model material and tested under four-line loads in order to obtain the material’s stress-strain relationship and flexural strength. Three wallettes will be tested for both orthogonal orientations of the material, i.e. six tests in total. It is assumed that construction of the wallettes will take 9 days, and 3 days are allowed for testing.
Construction of model
Following construction and testing of the wallettes, we intend to begin work on the model vault. Prior to this task, we will allow time for a 'dry' (without mortar) assembly of the model in order to determine the stability of the model during construction. This 'dry' assembly is not shown on the schedule. There have been 19 days allocated to the task of constructing the model. This is one of the most fundamental tasks in our schedule; more time can be allowed prior to examinations if deemed necessary.
Interim report preparation and write-up
The interim report is due on Friday 31st January and work on the report will begin on Monday 25th November. This should allow ample time before and after the Christmas exam period, whilst allowing focus to be directed towards the design project during the first two weeks of Semester 2. The interim report will present a summary of work completed to date, a comprehensive and critical review of all relevant literature studied, and a review of the planning document (including the project schedule shown above).
Lab tests (elastic)
The model will be subjected to evenly distributed lead weights to simulate self weight in the real structure, and the deformation will be monitored for varying heights of spandrel fill. A larger time window has been allocated to the elastic testing phase than the failure tests because it is essential that the model has time to return to its initial state after unloading. Failure to allow the model to recover between tests would lead to unreliable results.
Lab tests (failure)
A one week gap has been left after the elastic testing is completed before commencing the second testing phase. During the 'failure' test the model will be driven beyond the limits of serviceability by spreading the supports and driving the structure to collapse. Repairs will be carried out using FRP and their affect will be assessed. It is deemed that 12 days will be ample time to prepare and conduct this phase of testing.
Thesis write-up
It is intended that we will begin to write up our thesis during the week commencing Monday 3rd February. The thesis write up will take place in conjunction with the recording and analysis of results. Nine weeks in total have been allowed for the write-up; however it is intended that it will be written in seven weeks to allow a two week time window for proof reading, printing and binding.
Oral Presentation
Although this task will only take one day, four weeks have been allowed on the project schedule as the date shall not be confirmed until nearer the presentation. This will be an informal opportunity for the author to present the thesis to the second reader and project supervisor and for them to assess the author's depth of understanding of the project.
All photos are the property of Michael Scott or James Sanderson unless otherwise stated.
© 2013 James Sanderson and Michael Scott | All rights reserved.
School of Engineering, College of Science and Engineering, University of Edinburgh
© 2013 James Sanderson and Michael Scott | All rights reserved.
School of Engineering, College of Science and Engineering, University of Edinburgh